A data engineer schedules a Lakeflow Job to run every 15 minutes. Occasionally a run takes longer than 15 minutes. The engineer notices that the next scheduled run does not start while the previous run is still in progress, and wants to understand this behavior and change it if necessary. Which statement is correct?
Answer & explanation
Correct answer: E
WHY E: A job runs a single active run at a time by default, so an overlapping schedule tick is skipped; increasing the maximum concurrent runs setting allows overlapping runs. WHY NOT A: Skipped triggers are not all queued and replayed; the default behavior is to skip while a run is active, not guarantee every interval. WHY NOT B: The default is a single active run, not unlimited; the serialization is by design and cluster size is not the cause. WHY NOT C: An in-progress run is not cancelled and restarted by a new schedule tick; the running job continues and the tick is skipped. WHY NOT D: The concurrency limit is configurable, so cloning the job is unnecessary to allow overlapping runs.